To Build a Dock - Part 1
After 20 years of living on Lake Wylie, the time has come to build a new dock! The old one served us well, but is now badly splintered, loose in many places, and in need of much more than a fresh coat of paint.
Once I decided to totally replace my dock, I investigated design and material options. I wanted something that was low maintenance, durable, and easy on the feet. No splinters or blisters from hot surfaces!
I decided on an aluminum dock with a covered boat slip, with a gangway from a small landing on shore. I got price quotes from several different companies for materials and assembly. To save money, I decided to handle the assembly on my own. (This made my wife a little nervous, but she’s used to me making her nervous.)
Whether you’re building a new dock or refurbishing an old one, you must apply for a Lake Wylie dock permit from Duke Power. I am very familiar with the regulations for building docks and know my way through the dock permit process, as I am a real estate agent and have helped many of my clients in this area.
I called to get a dock permit application from Duke Energy Lake Services (800-443-5193). The requirements are all outlined in the Shoreline Management Guidelines, which are sent with the dock permit application. The allowed length, size, and boat slip capacity of the dock depends on such factors as water frontage of the lot, cove width measurements, and environmental considerations.
I found the York County GIS system very helpful in determining the requirements for my dock. (www.yorkcountygov.com). I was able to measure my lot’s waterfront dimensions as well as the dimensions of our cove. Then I was able to determine the maximum length and size of dock allowed, based on the Shoreline Management Guidelines.
When I filled out the dock permit application, I submitted required details: style of dock, proposed measurements, and total surface area. Then I had to make an appointment with a representative from Duke Energy Lake Services to review the site and plans. The representative met me at my house about 2 weeks after submitting the application, and was very helpful in helping me conform my design to Duke Energy dock guidelines. He pointed out that the angle of my planned dock would intersect my neighbor’s property line, so I needed to obtain my neighbor’s permission. He emailed me a Projected Property Line Approval Letter form, which my neighbor signed. I was set.
Within 3 weeks after submitting my dock permit application, I received a letter of approval authorizing the building of my dock! According to the letter, I have 12 months to complete the project. (According to my wife, I have about 3 weeks!).
Before anyone changed their minds, I ordered my materials. Stay tuned!
When you finish reading the blogs, see all the fun pictures by clicking on "Building the Dock: The Movie" at the top of the screen.
Visit my Lake Wylie Waterfront Real Estate for property searches, Resources for Lake Wylie Waterfront Property Owners, recommended service professionals, and more.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment